Section One: Programme Commentary, RAG and Resources Update
Programme Commentary
The LMP008 project commenced rollout of the Reading List on 12th June, the Library teams are actively working towards the deadline for Talis being expired on 10th July, the project is now in closure phase with a final Project Board meeting on 27th July and will be handed over to Service Board under the remit of Laura Shanahan.
A further meeting was held with Library colleagues and Finance team members on 4th July to review planning proposal 17/18 for Alma Two-way Feed with E-Financials, agreement was for 50 budget days in 17/18 will be used to commence business analysis activity to gather business requirements.
Overall Programme RAG: GREEN
Forward Look and RAG
Resource Position
Section Two: Projects Not Started
Project Info | Project Manager's Commentary |
N/A | |
Section Three: Projects in Progress
Project Info | Project Manager's Commentary | ||||
LMP008 Resource List software integration with Alma Library Management Platform D Milestones
RAG Status GREEN |
Report by Karen Stirling for June 2017 Achievements in Last Period
Issues
Next Steps
The project status is GREEN
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
LMP001 New Library Management Platform Procurement Discretionary |
Report By Karen Stirling This project was closed 6th March 2015 |
LMP002 Implementation of a next generation Library Services platform Discretionary |
Report By Karen Stirling This project was closed 11th September 2015 |
LMP003 LMP - EASE Integration Discretionary |
Report By Karen Stirling This project was closed 30th July 2015 |
LMP004 LMP - IDM Integration Discretionary |
Report By Karen Stirling This project was closed 3rd September 2015 |
LMP005 LMP - Integration with Finance Discretionary |
Report By Karen Stirling This project was closed 30th October 2015 |
LMP007 Online Fine Payments Discretionary |
Report by Morna Findlay Project was closed on 2nd September 2016 |
LMP006 Feeding Visitor data into Alma Discretionary |
Report By Karen Stirling This project was closed 24th February 2017 |