Report for June 2017

Report Date
June 2017

Achievements in Last Period

  • No progress was made in this period - a change to milestones is documented below

Issues

  • PICCL Change 7 - https://www.projects.ed.ac.uk/unpublished/project/com032/issues/7 , updated milestones, reported to WIS 30/6/17.  The closure of this project requires to be rescheduled.  This is due to a delay to fix the issue identified during UAT; automated emails to Service Management fail to be sent when a person opts out of the service (this requirement is documented in JIRA COM032-20).

Next Steps

  • Complete UAT
  • Close project

 

Target Datesort descending Title
31-Jul-2017 Closure
Project Status
RAG Status
Time
RED
Cost
GREEN
Scope
GREEN
Overall
RED
RAG Commentary
Change - PICCL Change 7 - https://www.projects.ed.ac.uk/unpublished/project/com032/issues/7 , updated milestones. The closure of this project requires to be rescheduled. This is due to a delay in fixing the issue identified during UAT; automated emails to Service Management fail to be sent when a person opts out of the service (this requirement is documented in JIRA COM032-20).
Change Status
Activity
Approved budget
85.0 days
Activity this month
0.8 days
Activity this year
85.0 days
Activity to date
85.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days