Report for May 2017

Report Date
May 2017

Achievements in Last Period

  • Closure report written and distributed for review. All feedback received has been incorporated.
  • Agreement on closure milestone and report at team meeting 08-Jun-17.

Issues

  • CLOSED: Delayed closure meeting as Business Lead unavailable due to British Airways IT failure. Closure meeting was re-planned for Thursday 08/06/2017.

Next Steps

  • Finalise project closure.

RAG Commentary

ISSUE - Delay to closure meeting due to 1) BA IT Failure.

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
Delayed closure meeting as Business Lead unavailable due to British Airways IT failure
Change Status
Activity
Approved budget
256.0 days
Activity this month
3.0 days
Activity this year
132.0 days
Activity to date
267.0 days
Estimate to complete current year
1.0 day
Estimate to complete future years
0.0 days