Report for May 2017

Report Date
May 2017

Achievements in Last Period

  • Review meeting held 25/07. See https://www.projects.ed.ac.uk/unpublished/project/est093/meetings/project-review-meeting-0
  • Karen Adamson has been appointed Project Sponsor
  • Colin Pritchard, Richard Mann are business leads for maintenance mgmt, space respectively. 
  • The project will re-start by re-viewing an updating the business analysis. We will do this in conjunction with DTI project DTI019.
  • The project will run in parallel with the project building EDW (DTI006) and as such will be an "early adopter" of EDW.  

Issues

  • None

Next Steps

  • Formally re-start project 
  • Engage MI/BI Business analyst
  • Review / update Maintenance Mgmt, Space Business Analysis
  • Plan build / execution phases  

The project is reporting GREEN.

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
200.0 days
Activity this month
1.5 days
Activity this year
19.7 days
Activity to date
58.9 days
Estimate to complete current year
22.9 days
Estimate to complete future years
123.0 days

Project Info

Not available.

Documentation

Not available.