Report for April 2017

Report Date
April 2017

Achievements in Last Period

  • As part of the process to continue reviewing the outstanding issues,
    • The monthly billing has been successfully implemented
    • The remaining issues have been reviewed and decisions taken to move these to a new Jira issue log for further review in version 23.1 
    • a total of 12 issues have been closed
    • review of remaining issues held with Mass on a weekly basis

Issues

  • Monthly billing, whilst now in operation, a few issues relating to the processing of archived invoices and credit notes have arisen and are currently being investigated. 

Next Steps

  • Requirement to resolve the priority issues  (noted below) and as many of the non-priority issues prior to closing the project in the next month
    • Changing Status on work request (currently under test)
    • Correct Employee-Id on weekly download (if now deemed as required)
  • Close project
  • Continue planning for version 23.1 upgrade incorporating technical aspects from the Lessons Learned report

 

Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
GREEN
Overall
BLUE
RAG Commentary
Issue: Project team continue to work at closing off post deployment snagging issues
Change Status
Activity
Approved budget
567.0 days
Activity this month
7.0 days
Activity this year
357.0 days
Activity to date
579.0 days
Estimate to complete current year
5.0 days
Estimate to complete future years
0.0 days