Achievements in the last period
- Service Management have carried out User Acceptance Testing and established that the data within the universe is accurate. A report to compare and contrast against current reporting was the basis of the testing.
- A JIRA containing final tweaks to the universe has been created. https://www.jira.is.ed.ac.uk/projects/SMI008/issues/SMI008-34?filter=allopenissues
- All other project documentation is complete other than the closure report which is in draft format.
- No more work will be done after this JIRA on SMI008.
Issues
- None
Next steps
- Complete JIRA 34.
- Close the project.
- Approved budget
- 175.0 days
- Activity this month
- 0.1 days
- Activity this year
- 23.4 days
- Activity to date
- 173.3 days
- Estimate to complete current year
- 1.0 day
- Estimate to complete future years
- 0.0 days