Report for April 2017

Report Date
April 2017

Achievements in Last Period

  • New infrastructure deployed into LIVE on 19/04

Issues and Risks

  • Some tweaks required to configuration of new servers

Next Steps

  • Sign off deployment
  • Prepare project completion and close project
  • Finalise answer on FASIC server

 

Milestones

28-Apr-2017 Deployment sign-off Deliver
12-May-2017 Project closure Close
Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
23.0 days
Activity this month
4.2 days
Activity this year
22.9 days
Activity to date
22.9 days
Estimate to complete current year
0.5 days
Estimate to complete future years
0.0 days

Project Info

Not available.