Report for March 2017

Report Date
March 2017

Achievements in Last Period

  • It has been agreed that the project can re-commence
  • Project has been re-planned for the remainder of the year to review the business requirements and determine business priorities

Issues

  • The impact on GASP, a key customer for the space subject area needs to be understood. A stop gap solution may be required.
  • The scope of COM029 doesn’t deliver a working set of DEV, TEST, LIVE EDW environments; therefore there will be a follow-on project (as yet undefined) which will deliver further EST093 pre-requisites.
  • The technical and development skills required for the project have been identified as a critical success factor.

Next Steps

  • A meeting has been arranged for early April to determine requirements from GASP
  • Review previously defined business requirements and priorities with Estates
  • Re-plan project to align with the Enterprise Date Warehouse project

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
200.0 days
Activity this month
1.0 day
Activity this year
17.0 days
Activity to date
57.0 days
Estimate to complete current year
25.0 days
Estimate to complete future years
122.0 days