Report for March 2017

Report Date
March 2017

Achievements in the last Period

  • Delivery signed off by Sponsor, see Delivery sign-off milestone.
  • Online survey created to gather feedback from user group members. The survey is based on the success criteria set by the user group in April 2016.

Issues

Next Steps

  • Circulate survey
  • Project report and closure

 

Project Status
RAG Status
Time
RED
Cost
GREEN
Scope
GREEN
Overall
RED
RAG Commentary
RED as closure milestone to be be moved due to business lead unavailability and to allow time for stakeholders to contribute to closure review.
Change Status
Activity
Approved budget
182.0 days
Activity this month
1.6 days
Activity this year
58.6 days
Activity to date
175.0 days
Estimate to complete current year
7.0 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation

Not available.