February 2017

Report Date
February 2017

 

The programme has several projects still to start, but programme owner and manager are working on securing the necessary resource through contractors to keep the goal of completing all work by end of July realistic.

The biggest threat to the programme is from the risk of losing contractors through IR35. We are waiting for projects services who as contractor suppliers are dealing with the risk (issue), to clarify the position on this.

 

Codesort descending Programme Owner and Manager Commentary RAG Manager Status Stage
RSS002

Roslin Research Computing Expansion

Not all the storage has been delivered due to external factors.

Way Forward ; Kenton and Kevin currently on a plan to take to Roslin by 17/3.

Intention is to put new PM Andy Todd on this to help drive it to second delivery and completion. 

 

RED Kenton D'Mellow In Progress Execute
RSS006

Data Safe Haven Pathfinder

 

BLUE Orlando Richards Closed Close
RSS008 New Service for Data Science BLUE Maurice Franceschi Closed Close
RSS016

Data Safe Haven Service

1. The two strands (Technical, Procedural) are underway. 2. KPMG have been engaged (as 27.0.0.1/IGT auditors) to advise on gaps and requirements to eventually reach accreditation for the service. 3. We have engaged with KPMG to provide a high level conceptual design and a high level component design. 4. Work is proceeding on technical design and implementation documents. 5. As part of this work we have identified external dependencies for technical implementation (eg. Networks, AD, etc) and are looking to engage as early as possible to mitigate risks around this. 6. We have started discussions with our framework supplier over options to have them support procuring and implementing a technical design. 7. We are engaging closely and directly with the Procedural strand of the project to keep the two strands as aligned as possible (given the very tight time scale).

As you'll all be aware this is a very ambitious project on a very tight time scale and requires considerable focus and resource.

Stephen and Thomas are currently (and until July) mainly focussed on delivery of this project and it is also identified as my (and the team's) highest priority for delivery.

 

 

RED Iain Moore-McLaughlin In Progress Execute
RSS017

Research Data Services DR Overhaul

The short term DR work is underway (although somewhat interrupted by AFM/DataStore service stability work). We need to properly set up a project for the medium term work and clarify what needs done (ie. a design/definition workshop, soonest).

Just need further discussions with DELL to ensure delivery.

AMBER Kirsty Waddell In Progress Plan
RSS018 DRS Outreach Programme  

This project has started and there are some activities we can count under this. However, we do need to come up with a defined plan of activities and associated costs. There is clearly a lot we could do to improve our profile with researchers in the university and this is an opportunity to do so. There has been some delay in this project until we got out of the AFM issues but now is the time for us to get planning.

AMBER David Fergusson In Progress Plan
RSS019 DataStore Refactor and Server Refresh  

We need to plan what expansion/refresh is needed for DataStore. We may need to be very pragmatic about this and just expand capacity, unless there are some easily and clearly identifiable updates that are required. One instance maybe provision of additional presentation layer nodes for colleges and re-factoring to separate 'home directory', cluster/analytical and research instrument capture streams. Possibly provision of a buffer space for high data through-put instrument data capture (eg. CMVM sequencing, new EM, etc).

Steve Taylor struggling to find space for this, so Andy Todd to be assigned.

GREEN Stephen Taylor In Progress Plan
RSS020

RCI Cloud and Data Science Services

Have started talking to suppliers. Have settled on what we want suppliers to provide. Jan and Steve working ahead of project. Andy Todd to be PM.

  Kenton D'Mellow Not Started Initiate
RSS021 Research computing infrastructure expansion   David Fergusson Not Started Initiate
RSS022 Data Vault  

DataVault is aimed at providing an internal research data archive for UoE (to support requirements coming from funding bodies and general good practice). The project was initially working with a JISC project on a software management layer and there is an expectation of an initial service as soon as possible. We have been engaging with the library team leading the project since the beginning of the year (formally since beginning February) to understand what is required to reach an initial service soonest. There is an issue with the initial software in handling large scale data sets (ie. those in scientific research particularly) and we have been advising the project team on possible ways forward with this.

One option, still under discussion, is greater use of Storage Manager to allow an initial service to be reached.

The current solution uses DataStore as the vault location and it is likely that this will be the case for the initial service (to get it in place). However, going forward we will have to look at a lower cost archive solution (probably tape).

  Stephen Taylor Not Started Initiate
RSS023

Backup Research infrastructure Upgrades

The short term DR work is underway (although somewhat interrupted by AFM/DataStore service stability work). We need to properly set up a project for the medium term work and clarify what needs done (ie. a design/definition workshop, soonest).

  Kevin Tomlinson Not Started Initiate
RSS024

Roslin expansion 16-17

we just need to work with the colleges to meet there requirements and funding cycles. Largely driven by them.

Waiting for Roslin to confirm they have funding.

Andy Todd to be assigned as PM - this is a procurement exercise

  Nicholas Moir Not Started Initiate
RSS025

IGMM expansions 16-17

we just need to work with the colleges to meet there requirements and funding cycles. Largely driven by them.

  David Fergusson Not Started Initiate
RSS026

RCI (Eddie) major version updates

As per Datastore re-factor and refresh.  

  David Fergusson Not Started Initiate
RSS027

DataStore Expansions

As per Datastore re-factor and refresh.

  David Fergusson Not Started Initiate
RSS028

Research Services Administration and Automation Application

We have selected a PM consultant from the candidates, and I think they should be good at driving the project forward. Kenton and Kevin will be the product owners for the project: ie. guide the requirements, what is to be implemented and also evaluate for acceptance. Apps are looking at finding the required development effort.

Jon March has been recruited and developers from Apps have been assigned, and a contractor starts 3rd April, so we need to get foundation done by then.

We need to confirm the new estimate for budget with the project team and then discuss with Tony.

 

 

  Jon March Not Started Initiate

Programme Info

Not available.

Documentation

Not available.