Report for February 2017
- Report Date
- February 2017
Achievements in Last Period
- Whilst the project is currently suspended a meeting has been held with the Enterprise Data Warehouse Project Team to determine current status of programme and how this will impact on the Estates Strategic Reporting project
Issues
- The impact on GASP, a key customer for the space subject area needs to be understood. A stop gap solution may be required.
- The scope of COM029 doesn’t deliver a working set of DEV, TEST, LIVE EDW environments; therefore there will be a follow-on project (as yet undefined) which will deliver further EST093 pre-requisites.
- The technical and development skills required for the project have been identified as a critical success factor.
Next Steps
- Commence project review early March.
- Determine requirements from GASP
- Review previously defined business requirements and priorities with Estates
- Re-plan project to align with the Enterprise Date Warehouse project
The project is currently suspended
- Approved budget
- 200.0 days
- Activity this month
- 0.1 days
- Activity this year
- 16.2 days
- Activity to date
- 55.4 days
- Estimate to complete current year
- 26.1 days
- Estimate to complete future years
- 119.5 days