Report for February 2017

Report Date
February 2017

Achievements in Last Period

  • PPM successfully run on the live environment
  • As part of the process to continue reviewing the outstanding issues,
    • further 6 issues have been closed
    • review of remaining issues held with Mass
    • a further 3 fixes have been received and applied, but will require a further tomcat re-start to implement the changes
    • requirement for business to review and determine strategy regarding the individual issues
  • Monthly billing UAT completed successfully on Test
  • Initial DSOR meeting held with IS Applications Management - no performance or functional concerns with the live service
  • Project completion report completed and circulated
  • Lessons learnt process has commenced
  • Andy Stewart has been assigned as project manager to close out the project

Issues

  • Unexpected issue encountered on the webcentral url which prevented approval of multiple jobs  and the inability to assign a craftsperson a work request. Resolved after a tomcat re-start
  • Monthly billing process not signed off as issues encountered whilst running in the live environment
  • 21 issues remain on the current outstanding list  
  • Delays in delivery of EST092 Operational Reports.
  • Additional budget will be required to complete the project

Next Steps

  • Requirement to re-plan remaining project activities
  • Complete Monthly billing UAT, and implement
  • Complete Lessons learned
  • Continue to focus on closing the appropriate outstanding issues for this project
  • Complete Deployment Sign-off and Closure

 

Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
BLUE
Overall
BLUE
RAG Commentary
Issue: Additional time and budget will be required to bring the project to conclusion. Project manager is working with the business to agree a completion date. Additional budget has been approved by programme manager
Change Status
Activity
Approved budget
505.0 days
Activity this month
30.1 days
Activity this year
327.8 days
Activity to date
549.6 days
Estimate to complete current year
17.3 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation

Not available.