February 2017
- Report Date
- February 2017
Achievements in Last Period
- Contract negotiations continued into February with final changes made by Procurement and Legal w/c 20/02/17 for agreement and signing w/c 27/02/17.
Issues
- No major issues; contract negotiations complete.
Next Steps
- Get contract signed off by all parties.
- Agree (procurement) project closure.
The project current status is AMBER due to delays finalising and signing contract. With this issue resolved the status will return to GREEN.
Milestones
(NB outstanding milestones now pushed into March due to delay getting final contract version available for signing)
| 13-Feb-2017 | Contract Signed |
| 20-Feb-2017 | Closure |
- Approved budget
- 175.0 days
- Activity this month
- 3.0 days
- Activity this year
- 50.0 days
- Activity to date
- 179.0 days
- Estimate to complete current year
- 1.0 day
- Estimate to complete future years
- 0.0 days