February 2017

Report Date
February 2017

Achievements in Last Period

  • Contract negotiations continued into February with final changes made by Procurement and Legal w/c 20/02/17 for agreement and signing w/c 27/02/17.

 

Issues

  • No major issues; contract negotiations complete.

 

Next Steps

  • Get contract signed off by all parties.
  • Agree (procurement) project closure.

The project current status is AMBER due to delays finalising and signing contract. With this issue resolved the status will return to GREEN.

 

Milestones

(NB outstanding milestones now pushed into March due to delay getting final contract version available for signing)

13-Feb-2017 Contract Signed
20-Feb-2017 Closure
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
175.0 days
Activity this month
3.0 days
Activity this year
50.0 days
Activity to date
179.0 days
Estimate to complete current year
1.0 day
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation

Not available.