Report for January 2017
- Report Date
- January 2017
Report by Muriel Mewissen for Bruce Nelson (Portfolio Owner)
Section One: Programme Commentary, RAG and Resources Update
Commentary:
During January, the only project activity was in SCEP02 - Virtual Edinburgh PM Consultancy and Support, resulting in 3 days being utilised by IS Applications across the programme.
The CSCE Programme / Portfolio has a budget of 211 days for 2016/17 with 95 days still unassigned. Its overall status is AMBER. Please note that the project RAG status is following the guidelines available on the Project RAG status guidance page.
Of interest:
- COM032 - Rollout Academic Timetable Integration with Office 365 Calendar
- COM022 - Academic Timetable Integration With Office 365 Calendar.
Forward Look - January 2017:

Resources to end January 2017:

Section Two: Projects Not Started
| Project Info | Programme Manager's Commentary |
|
AP67-073 16/17 Ring Fenced Allocation for CSCE GREEN |
95 days of core funding remains to be allocated (out of 150 days). The current allocations are:
|
Section Three: Projects in Progress
| Project Info | Project Managers Commentary | ||||
SCE010 (AP56-925)Athena Swan Reporting Improvements
Category: Discretionary Milestones
RAG Status AMBER |
Report by Susan Duff for January 2017 Achievements:
Issues:
Next Steps:
Amber as although agreement reached to move to closure, closure milestone has moved
|
||||
SCEP02:Virtual Edinburgh PM Consultancy and Support
Category: Discretionary Milestones n/a RAG Status GREEN |
Report by Morna Findlay for January 2017 No report available |
||||
SCE011: ExamOnline Trial
Category: Discretionary
Milestones
RAG Status AMBER |
Report by Muriel Mewissen for January 2017 Achievements this period
Issues
Next steps
|
Section Four: Closed or Withdrawn Projects
| Project Info | Project Manager Commentary |
|---|---|
| N/A | Projects in the CSCE programme for 16/17 are currently in progress or are yet to start. |
| Attachment | Size |
|---|---|
| 87.95 KB | |
| 98.89 KB |