Monthly Report
- Report Date
- December 2016
Achievements in Last Period
- Decision has been taken to suspend the project, with a review date set for early March. See https://www.projects.ed.ac.uk/unpublished/project/est093/issues/6 for further info.
Issues
- The impact on GASP, a key customer for the space subject area needs to be understood. A stop gap solution may be required.
- The scope of COM029 doesn’t deliver a working set of DEV, TEST, LIVE EDW environments; therefore there will be a follow-on project (as yet undefined) which will deliver further EST093 pre-requisites.
- The technical and development skills required for the project have been identified as a critical success factor.
Next Steps
- Conduct project review early March.
The project will report GREEN until such time as a project re-boot is initiated.
- Approved budget
- 200.0 days
- Activity this month
- 1.3 days
- Activity this year
- 15.4 days
- Activity to date
- 54.6 days
- Estimate to complete current year
- 26.5 days
- Estimate to complete future years
- 119.5 days