Monthly Report
- Report Date
- December 2016
Achievements in Last Period
- Project re-planned around the 25/01 go-live date and governance papers submitted and approved.
- Background and Legacy testing still in progress; all other testing complete.
- Response time issues objectively evaluated and a plan of action agreed.
- Business continuity plan agreed.
- Detailed GO LIVE planning (SOE) at an advanced stage, with additional focus being provided by IS.
- Additional IS resource allocated to cover January training sessions.
Issues
- Delays in getting background UAT executed & signed-off, impacting on acceptance sign-off.
- Delays in delivery of EST092 Operational Reports.
Next Steps
- Complete Background / Legacy UAT
- Complete Acceptance Sign-off.
- Complete Training delivery.
- Complete detailed GO LIVE (SOE) Planning & preparation.
- GO LIVE
The project is reporting AMBER, subject to Background / Legacy UAT sign-off.
- Approved budget
- 505.0 days
- Activity this month
- 32.8 days
- Activity this year
- 237.2 days
- Activity to date
- 458.9 days
- Estimate to complete current year
- 67.6 days
- Estimate to complete future years
- 0.0 days