Monthly Report

Report Date
December 2016

Achievements in Last Period

  • Project re-planned around the 25/01 go-live date and governance papers submitted and approved.
  • Background and Legacy testing still in progress; all other testing complete.  
  • Response time issues objectively evaluated and a plan of action agreed.
  • Business continuity plan agreed. 
  • Detailed GO LIVE planning (SOE) at an advanced stage, with additional focus being provided by IS. 
  • Additional IS resource allocated to cover January training sessions.    

Issues

  • Delays in getting background UAT executed & signed-off, impacting on acceptance sign-off.
  • Delays in delivery of EST092 Operational Reports.

Next Steps

  • Complete Background / Legacy UAT
  • Complete Acceptance Sign-off.
  • Complete Training delivery.
  • Complete detailed GO LIVE (SOE) Planning & preparation.
  • GO LIVE

The project is reporting AMBER, subject to Background / Legacy UAT sign-off.

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
505.0 days
Activity this month
32.8 days
Activity this year
237.2 days
Activity to date
458.9 days
Estimate to complete current year
67.6 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation

Not available.