TEL034: Lynda.com Implmentation: BI/BO POC to LIVE

Report Date
December 2016

Achievements this period

Implementation Plan complete

OLA complete

JH 1:1 training completed

Issues

https://www.projects.ed.ac.uk/unpublished/project/tel034/issues/40

Next Steps

Integration completed

Peer testing complete

Test available

UAT completed and signed off

Deployment Checklist completed

Handover/Deploy

Closure report completed/signed off

Project closed

Milestones

Target date

Title

Complete

13/05/16

Planning

YES

11/01/17 (13/12/16)

Delivery

NO

31/01/17 (22/12/16)

Closure

NO

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
109.0 days
Activity this month
7.0 days
Activity this year
59.0 days
Activity to date
98.5 days
Estimate to complete current year
10.0 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation

Not available.