November 2016

Report Date
November 2016

Achievements last period

  • Evasys text responses enabled in Course Evaluation universe
  • Further universe changes to handle multi-response questions and revised staff question sets implemented
  • Implemented in-house solution to surfacing text responses in BIS universe
  • Course Evaluation and NSS survey outcomes published in beta version on 'Data Matters' website
  • Automation of two-level dashboard security based on user authorisation implemented
  • Google Analytics enabled on dashboards
  • Milestones replanned – closure Jan 2017 to cover Course Evaluation semester 1 reporting
  • Staff report publication proof of concept undertaken

Open Issues

Resolved Issues

  •  

Next Steps

 

Closure 31/1

Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
220.0 days
Activity this month
9.0 days
Activity this year
60.0 days
Activity to date
229.0 days
Estimate to complete current year
12.0 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation

Not available.