TEL034: Lynda.com Implementation

Report Date
November 2016

Achievements this period

None

Issues

https://www.projects.ed.ac.uk/unpublished/project/tel034/issues/38

Next Steps

Integration completed

Peer testing complete

Test available

1:1 training/UAT completed and signed off

Deployment Checklist completed

OLA reviewed and signed off

Handover/Deploy

Closure report completed/signed off

Project closed

Milestones

Target date

Title

Complete

13/05/16

Planning

YES

13/12/16

Delivery

NO

22/12/16

Closure

NO

Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
104.0 days
Activity this month
5.0 days
Activity this year
51.5 days
Activity to date
90.0 days
Estimate to complete current year
12.0 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation

Not available.