Report for October 2016

Report Date
October 2016

Achievements:

  • Update draft brief

Issues:

  • Planning delayed due to competing priorities and PM leave. WIS approve change in planning milestone on 21 October 2016, see issue 1.

Next Steps:

  • Complete Project planning

Next Milestone:

Project brief to be completed by 11 November 2016

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
250.0 days
Activity this month
0.6 days
Activity this year
9.2 days
Activity to date
15.4 days
Estimate to complete current year
200.6 days
Estimate to complete future years
34.0 days

Project Info

Not available.

Documentation

Not available.