October Report

Report Date
October 2016

Achievements in Last Period

  • Draft Disaster Recovery Plan issued out for review and agreement by project team

Issues

  • Due to Project manager's annual leave during October  limted activity completed on project
  • DR repository has still to be created - waiting for confirmation TADs can be uploaded onto SharePoint Site - Project Sponsor proposing this to OGG, also Service Management resource availability to support repository creation.
  • Project milestones to be reviewed and resource effort estimated for final activity on project - budget review for funding to be returned to the INF programme

Next Steps

  • Update Sharepoint site with key documentation
  • DR plans updated where required
  • Review project resource estimates, returning potential unused days back to programme
  • Following Major Incident in mid September impacting KB, a template document to be created for information on priority services to be included within project

 

The project status is GREEN

21-Oct-2016 DR Document Storage Area ready
21-Oct-2016 Priority Services DR Documentation complete
14-Nov-2016 Delivery Complete
02-Dec-2016 Closure

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
100.0 days
Activity this month
1.3 days
Activity this year
10.5 days
Activity to date
27.6 days
Estimate to complete current year
68.5 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation

Not available.