October Report
- Report Date
- October 2016
Achievements in Last Period
- Draft Disaster Recovery Plan issued out for review and agreement by project team
Issues
- Due to Project manager's annual leave during October limted activity completed on project
- DR repository has still to be created - waiting for confirmation TADs can be uploaded onto SharePoint Site - Project Sponsor proposing this to OGG, also Service Management resource availability to support repository creation.
- Project milestones to be reviewed and resource effort estimated for final activity on project - budget review for funding to be returned to the INF programme
Next Steps
- Update Sharepoint site with key documentation
- DR plans updated where required
- Review project resource estimates, returning potential unused days back to programme
- Following Major Incident in mid September impacting KB, a template document to be created for information on priority services to be included within project
The project status is GREEN
21-Oct-2016 | DR Document Storage Area ready |
21-Oct-2016 | Priority Services DR Documentation complete |
14-Nov-2016 | Delivery Complete |
02-Dec-2016 | Closure |
- Approved budget
- 100.0 days
- Activity this month
- 1.3 days
- Activity this year
- 10.5 days
- Activity to date
- 27.6 days
- Estimate to complete current year
- 68.5 days
- Estimate to complete future years
- 0.0 days