Report for August
- Report Date
- August 2016
Achievements in Last Period
- Business analysis: Space Mgmt complete and signed-off.
- Business analysis: Maintenance Mgmt complete, and in final sign-off cycle.
Issues
- No project sponsor.
- Project is dependent upon the outputs of-outcomes from project COM025 (BI/MI architecture), and the emerging project COM029 (EDW build). Both of these projects are rpeorting delays against original milestones. .
- The technical and development skills required for the project have been identified as a critical success factor. Discussions are on-going with the head of development services.
- PM Resource constraint with EST080, leading to additional delays.
Next Steps
- Complete business scoping.
- Complete detailed business analysis.
- Re-align project milestones.
The project is reporting RED as no sponsor is currently assigned, and the project lacks impetus within Estates compared to other, higher priority initiatives.
- Approved budget
- 200.0 days
- Activity this month
- 10.7 days
- Activity this year
- 10.7 days
- Activity to date
- 49.9 days
- Estimate to complete current year
- 154.3 days
- Estimate to complete future years
- 0.0 days