TEL034: Lynda.com Implementation
- Report Date
- August 2016
Achievements this period
Data Archiving process agreed and drafted
Presentation to SMT
LEARN andMoodle integration showcased
POC SDS reviewed and signed off
Issues
Delays in decision making to scope and sign off of BRD
https://www.projects.ed.ac.uk/project/tel034/issues/27
Project Re-Plan - Remaining Deliverables
https://www.projects.ed.ac.uk/project/tel034/issues/30
Business Lead Annual Leave
https://www.projects.ed.ac.uk/project/tel034/issues/31
Next Steps
Agree revised milestones for remaining deliverables
Agree resource requirements to deliver remaining milestones
Milestones
Target date | Title | Complete |
13/05/16 | Planning | YES |
24/11/16 | Delivery | NO |
25/11/16 | Closure | NO |
- Approved budget
- 64.0 days
- Activity this month
- 27.5 days
- Activity this year
- 27.5 days
- Activity to date
- 67.0 days
- Estimate to complete current year
- 1.0 day
- Estimate to complete future years
- 0.0 days