August Report

Report Date
August 2016

Achievements in Last Period

  • Monitoring Data Quality following Soft Launch
  • Deployment Checklist completed
  • Project Closure Questionnaire completed and comments added to completion report
  • Completion report drafted and agreed at Deployment Sign Off review meeting which confirmed both DSOR and Closure sign off

Issues

  • Extended milestones to end of August for Deployment review sign off as Student data hasn’t been processed through to allow data monitoring to take place.
  • Completed a test course in Live for 15/16 to follow data through and then delete, this proved successful in seeing data being passed through

Next Steps

  • Project Closed WIS approval 02/09

 

The project status is GREEN

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
BLUE
Change Status
Activity
Approved budget
88.0 days
Activity this month
3.2 days
Activity this year
88.0 days
Activity to date
88.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days