August Report
- Report Date
- August 2016
Achievements in Last Period
- Monitoring Data Quality following Soft Launch
- Deployment Checklist completed
- Project Closure Questionnaire completed and comments added to completion report
- Completion report drafted and agreed at Deployment Sign Off review meeting which confirmed both DSOR and Closure sign off
Issues
- Extended milestones to end of August for Deployment review sign off as Student data hasn’t been processed through to allow data monitoring to take place.
- Completed a test course in Live for 15/16 to follow data through and then delete, this proved successful in seeing data being passed through
Next Steps
- Project Closed WIS approval 02/09
The project status is GREEN
- Approved budget
- 88.0 days
- Activity this month
- 3.2 days
- Activity this year
- 88.0 days
- Activity to date
- 88.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days