July Report
- Report Date
- July 2016
Achievements in Last Period
- User Acceptance signed off
- Updated Implementation ready for live deployment on 19th July
- Handover to Application Management completed
- Deployment to Live completed for soft launch
- Monitoring Data Quality following Soft Launch
Issues
- Development work aligned to Course Code fix being completed via ITS RDS Service Management budget requires resource to start work as key developer not available until August
Next Steps
- Ongoing Monitoring of Data Quality following Soft Launch
- Deployment Sign off review
- Project Closure
The project status is GREEN
16-Aug-2016 | |
30-Aug-2016 |
- Approved budget
- 88.0 days
- Activity this month
- 8.0 days
- Activity this year
- 80.0 days
- Activity to date
- 85.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 4.0 days