July Report

Report Date
July 2016

Achievements in Last Period

  • User Acceptance signed off
  • Updated Implementation ready for live deployment on 19th July
  • Handover to  Application Management completed
  • Deployment to Live completed for soft launch
  • Monitoring Data Quality following Soft Launch

Issues

  • Development work aligned to Course Code fix being completed via ITS RDS Service Management budget requires resource to start work as key developer not available until August

Next Steps

  • Ongoing Monitoring of Data Quality following Soft Launch
  • Deployment Sign off review
  • Project Closure

 

The project status is GREEN

 

16-Aug-2016

Deployment Review complete

30-Aug-2016

Closure

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
88.0 days
Activity this month
8.0 days
Activity this year
80.0 days
Activity to date
85.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
4.0 days

Project Info

Not available.

Documentation

Not available.