July Report
- Report Date
- July 2016
Achievements in Last Period
- Analysis activity in progress only a few remaining services to be reviewed for information e.g. Cloud based services and services owned by other areas such Network Shared Drives and Staff Mail
- Dash Board now being updated with key information
- High levels requirements created for repository and commencing discussions with Service Management regarding SharePoint site
Issues
- Review with Head of Production Management services which could potentially be removed as priority services e.g. Exchange Mail & Diary and Electronic Journals
Next Steps
- Agree storage options for a master DR document which can be stored off site
- Confirm what documentation is missing / needs to be created for services
The project status is GREEN
- Approved budget
- 100.0 days
- Activity this month
- 7.0 days
- Activity this year
- 17.0 days
- Activity to date
- 17.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 78.0 days