Report for July 2016
- Report Date
- July 2016
Achievements in Last Period
- All issues, with the exception of JIRA 76, have been resolved and re-tested
- Fix for remaining issue, JIRA 76, has been applied to the DEV environment and final checks by Supplier are in progress ahead of HR systems completing their final testing on DEV and TEST.
- Accessibility testing of v21 has been scheduled to take place on 23 August.
- Budget has been reduced by 7 days to 158 days: this reflects PM time no longer being recorded against the proejct being offset against the additional work that has been required to support the resolution of the JIRAs in DEV and TEST. There is more effort being continued into 16/17 than originally planned.
- Demo of TestRail to IS Senior Supplier and Head of Development Services was positively received and IS Applications will be pursuing implementing this type of software as another success factor in projects.
Issues
- None
Next Steps
- Minor release testing to be completed by CoreHR
- Final HR System testing - minor release for JIRA 76 fix on DEV and TEST
- Special CAB approval for delivery date to be requested
- Accessibility testing to be completed
Milestones
05-Aug-2016 | Final testing by HR Systems |
09-Sep-2016 | Completion of prep work on LIVE |
16-Sep-2016 | Completion of TEST Environment/Acceptance Sign-off |
28-Sep-2016 | Delivery |
12-Oct-2016 | Delivery Sign-off |
12-Oct-2016 | Completion of Major Governance Assessment Review |
28-Oct-2016 | Closure |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days