June 2016
- Report Date
- June 2016
Achievements in Last Period
- Supplier scenario demos took place as scheduled during period w/c 30/05/16 to w/c 17/06/16; some clarifications for each supplier.
- Consensus scores agreed for most sections of supplier written responses (pending some clarifications outstanding with suppliers).
- Project Board updated 21/06/16 and briefed on the outstanding issues for resolution (min threshold functionality issue for 1 supplier, and min threshold accessibility for 2 suppliers).
- Additional Project Board arranged for w/c 04/07/16 to reconvene and discuss resolution of outstanding issues.
Issues
- Further clarifications pending with one supplier regarding min threshold section of clinincal scenario. Project Sponsor, Procurement Manager and PM holding conf call with supplier to clarify.
- Discussions not yet complete with all suppliers regarding required work to meet Accessibility min threshold by implementation.
Next Steps
- Complete evaluation of suppliers (consensus on scoring of supplier written reponses and scenario demos, and commercials).
- Prepare recommendation for Project Board.
- Review risks with Project Board.
- Review budget and resourcing.
The project current status is AMBER due to delay reaching decision.
Milestones
(timeline to be reviewed at additional Project Board meeting w/c 04/07/16 and revised)
| 20-Jun-2016 | Award Recommendation |
| 21-Jun-2016 | Award Letter |
| 15-Aug-2016 | Contract Signed |
| 02-Sep-2016 | Closure |
- Approved budget
- 147.0 days
- Activity this month
- 15.0 days
- Activity this year
- 121.0 days
- Activity to date
- 121.0 days
- Estimate to complete current year
- 25.0 days
- Estimate to complete future years
- 11.0 days