Report for May 2016

Report Date
May 2016

Achievement this period

  • Analysis of 'as is' process is complete
  • Statistics compiled on Serengeti reliability

Issues

  • The analysis has been more complex than anticipated as the current processwas not well understood or documentated.  This has resulted in a need for an additional 4 days budget to complete the analysis summary.
  • Due to annual leave and resource conflicts from higher priority projects, the analysis sign-off and closure have been moved out by 2 weeks.
  • As a result of these two issues the project is being reported on AMBER

Next steps

  • Complete write-up of summary & recommendations document

 

Target dateTitle
01-Jul-2016End of analysis
15-Jul-2016Closure
Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
6.0 days
Activity this month
2.0 days
Activity this year
8.0 days
Activity to date
8.0 days
Estimate to complete current year
2.0 days
Estimate to complete future years
0.0 days