June Report

Report Date
June 2016

Achievements in Last Period

  • Commenced Analysis activity to review all applications & components which make up the Top Priority Services (12 in total)
  • Template created to capture relevant information and dash board format produced, currently using this as an Excel spreadsheet via One Drive
  • Identified that there will be services which are currently on old version of Technical Architecture Document – team agreed the project would not transfer to new format at this stage
  • Graeme Wood to be ITI contact for project

Issues

N/A

Next Steps

  • Continue analysis review for Medium Priority Services
  • Review and agree storage options for a master DR document which can be stored off site

The project status is GREEN

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
100.0 days
Activity this month
5.3 days
Activity this year
9.0 days
Activity to date
9.0 days
Estimate to complete current year
16.5 days
Estimate to complete future years
74.9 days

Project Info

Not available.

Documentation

Not available.