- June 2016
Achievements
- Iteration 3 materials delivered to CogBooks on time – now in their QA process
Issues
- No further updates from lead editor on feedback survey – assuming this has not been delivered and will go into closure as a deliverable not achieved
Next steps
- Waiting on CogBooks updating us with regards to contract costs
- DSOR – 25 July
- Close 29 July
Milestones