Report for June 16

Report Date
June 2016

Achievements

  • Iteration 3 materials delivered to CogBooks on time – now in their QA process

Issues

  • No further updates from lead editor on feedback survey – assuming this has not been delivered and will go into closure as a deliverable not achieved

Next steps

  • Waiting on CogBooks updating us with regards to contract costs
  • DSOR – 25 July
  • Close 29 July

 

Milestones

25-Jul-2016Deployment review
29-Jul-2016Close
Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
30.0 days
Activity this month
1.0 day
Activity this year
19.0 days
Activity to date
19.0 days
Estimate to complete current year
11.0 days
Estimate to complete future years
0.0 days