Report for June 2016

Report Date
June 2016

Achievements this Period

  • Further monitoring of CF migrations - all now completed
  • Related wiki pages and reports updated
  • All LSA migrations now effected except one (HR - planned for early July)
  • Red Hat & Solaris machines now availble for switching off

Issues

  • Technology Management time limited for work on some migrations

Next Steps

  • Final migrations to be completed
  • Project closure to be drafted and circulated
  • Project to be closed

 

Milestones

30-Jun-2016Windows decommissioning (15-16) completedDeliver
30-Jun-2016RedHat decommissioning (15-16) completedDeliver
30-Jun-2016Solaris decommissioning (15-16) completedDeliver
28-Jul-2016ClosureClose
Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
253.0 days
Activity this month
12.4 days
Activity this year
97.1 days
Activity to date
248.9 days
Estimate to complete current year
2.5 days
Estimate to complete future years
0.0 days