May 2016

Report Date
May 2016

Achievements in the last period

  • Test platform upgraded and refreshed.
  • Load / capacity testing planned w/c 06/06/16.
  • Liaison with TEL025 PM to ensure testing can progress on Moodle test.

Issues

  • No major issues at present.

Next steps

  • Testing, UAT, and progress to Acceptance as per the plan.

 

Milestones

24-Jun-2016Acceptance
11-Jul-2016Deployment
22-Jul-2016Deployment Sign Off
29-Jul-2016Project Closure
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
58.0 days
Activity this month
8.0 days
Activity this year
23.0 days
Activity to date
23.0 days
Estimate to complete current year
32.0 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation