TEL034: Lynda.com Implementation - DRAFT
- Report Date
- May 2016
Achievements this period - Soft Launch
Project Brief signed off/WIS signed off
Soft Launch Business Requirements defined and signed off
Data Protection policy and archiving process yet to be established signed off (hence delay)
Business ownership and administrational accountabilities identified
Technical design defined (based on current understanding but this may change dependant on Data Protection/Archiving decision)
Issues
Changes to scope and delivery date - SOFT LAUNCH
https://www.projects.ed.ac.uk/project/tel034/issues/12
Next Steps - Soft Launch
Issue comms to affected parties
Issue comms advising downtime for Lynda.com users during UAT
Issue general Soft Launch comms
Create Webpage landing site for access to Lynda.com
UAT
Soft Launch release
Milestones - SOFT LAUNCH
Target date | Previous Date | Title | Complete |
13/05/16 | 29/04/16 | Planning | YES |
16/06/16 | 18/07/16 | Delivery | NO |
10/10/16 | 01/08/16 | Closure | NO |
- Approved budget
- 24.0 days
- Activity this month
- 13.3 days
- Activity this year
- 17.1 days
- Activity to date
- 17.1 days
- Estimate to complete current year
- 4.3 days
- Estimate to complete future years
- 3.3 days