Report for May 2016
- Report Date
- May 2016
Achievements in Last Period
- Complete DEV Upgrade milestone achieved
- TEST ready for UAT milestone achieved
- User group UAT took place as scheduled
- Resolution of some JIRAs
- Planning for LIVE build underway
Issues
- Further issues were raised during the User Group UAT and these are requiring the Supplier's Development team to provide weeks of unplanned re-work. An escalation process has been activated with the supplier to secure the resources, with delivery of the major issue (JIRA 76) expected w/c June 10. The delay due ot these issues and the additional unplanned effort to support this re-work means the project needs re-estimted and re-scheduled. The re-estimation will take place on 13/06/16 and based on the supplier's progress with the issue, the project will then be re-planned. Due to leave across the team in July and August, it is expected that the project's delivery date will slip by over a month and therefore the project's RAG status is being set to RED.
Next Steps
- Supplier to complete resolution of issues in DEV
- Complete HR Systems re-testing in DEV and TEST (the UAT Sign-off milestone will be moved to follow this testing)
- Complete stage 1 in LIVE
- Complete stages 2 & 3 in TEST
- Upgrade TEST BI
- Complete Stages 2 & 3 LIVE
Milestones
30-May-2016 | UAT Sign-off |
17-Jun-2016 | Completion of prep work on LIVE |
11-Jul-2016 | Completion of TEST Environment |
27-Jul-2016 | Delivery |
10-Aug-2016 | Delivery Sign-off |
01-Sep-2016 | Completion of Major Governance Assessment Review |
30-Sep-2016 | Closure |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days