Report for May 2016

Report Date
May 2016

Achievements in Last Period

  • Complete DEV Upgrade milestone achieved
  • TEST ready for UAT milestone achieved
  • User group UAT took place as scheduled
  • Resolution of some JIRAs
  • Planning for LIVE build underway  

Issues

  • Further issues were raised during the User Group UAT and these are requiring the Supplier's Development team to provide weeks of unplanned re-work. An escalation process has been activated with the supplier to secure the resources, with delivery of the major issue (JIRA 76) expected w/c June 10. The delay due ot these issues and the additional unplanned effort to support this re-work means the project needs re-estimted and re-scheduled. The re-estimation will take place on 13/06/16 and based on the supplier's progress with the issue, the project will then be re-planned. Due to leave across the team in July and August, it is expected that the project's delivery date will slip by over a month and therefore the project's RAG status is being set to RED.

 

Next Steps

  • Supplier to complete resolution of issues in DEV
  • Complete HR Systems re-testing in DEV and TEST (the UAT Sign-off milestone will be moved to follow this testing)
  • Complete stage 1 in LIVE
  • Complete stages 2 & 3 in TEST
  • Upgrade TEST BI
  • Complete Stages 2 & 3 LIVE

Milestones

30-May-2016UAT Sign-off
17-Jun-2016Completion of prep work on LIVE
11-Jul-2016Completion of TEST Environment
27-Jul-2016Delivery
10-Aug-2016Delivery Sign-off
01-Sep-2016Completion of Major Governance Assessment Review
30-Sep-2016Closure
Project Status
RAG Status
Time
RED
Cost
AMBER
Scope
GREEN
Overall
RED
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation

Not available.