Monthly Project Report

Report Date
May 2016

Achievements:

  • eTime TAD completed
  • JAMS TAD completed and updated (3-Jun)
  • Migrated eTime environment in DEV
  • DEV Build for eTime completed
  • Dev Tech resourcing bookings resolved
  • Migrate JAMS environment in DEV
  • Build JAMS in DEV
  • Migrated eTime environment in TEST
  • Migrate JAMS environment in TEST
  • Load balancer updated (Unix) for Dev and Test for JAMS and eTime
  • Revised Milestones and Budget approved

Issues:

  • Additional 15 days budget required to cover technical issues encountered in Dev, plus further delayed delivery & closure milestones, therefore the project is reported on RED this month.

Next Steps:

  • eTime TAD updated (6-Jun)
  • Acceptance Test eTime in TEST
  • Acceptance Test JAMS in TEST
  • Live prep for eTime
  • Live prep for JAMS
  • Load balancer updated (Unix) for Live for JAMS and eTime
  • eTime LIVE
  • JAMS LIVE
  • DSOR for eTime
  • DSOR for JAMS

Project RAG status of RED

Milestones

DateMilestone
10-Jun-2016Acceptance for eTime
13-Jun-2016Acceptance for JAMS
15-Jun-2016Live for eTime
22-Jun-2016LIVE for JAMS
29-Jun-2016DSOR for eTime
6-Jul-2016DSOR for JAMS
6-Jul-2016Closure
Project Status
RAG Status
Time
AMBER
Cost
RED
Scope
GREEN
Overall
RED
Change Status
Activity
Approved budget
65.0 days
Activity this month
22.0 days
Activity this year
46.0 days
Activity to date
46.0 days
Estimate to complete current year
20.0 days
Estimate to complete future years
0.0 days