May Report

Report Date
May 2016

Achievements in Last Period

  • Planning activities completed following review of project brief, plan and estimates
  • Stakeholder and Risk Logs created
  • High level review of disaster recovery plans available for Top and Medium priority services to assist completion of project brief
  • Project brief approved at WIS  on 03/06/16
  • Resource allocated from Dev Tech and Tech Man
  • Project team meetings set up for every 2 weeks

Issues

  • N/A

Next Steps

  • Commence Analysis activity to review all applications & components which make up the Top and Medium priority services (27 in total)
  • Review storage options for a master DR document which can be stored off site

The project status is GREEN

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
100.0 days
Activity this month
3.2 days
Activity this year
3.4 days
Activity to date
3.4 days
Estimate to complete current year
33.5 days
Estimate to complete future years
61.0 days