Report for May 2016
- Report Date
- May 2016
Achievements in Last Period
Project planning phase completed.
Project business scoping started.
Detail business analysis started.
Issues
Change of Sponsor. Current sponsor has stepped down from current post, and a replacement is being sought.
A number of risks have been raised regarding the dependencies of this project on others: - - Outcomes from project COM025 - Plans for the building of infrastructure in support of EDW - The availability and skillsets need for application development.
Next Steps
Complete business scoping.
Continue with detailed business analysis.
- Approved budget
- 200.0 days
- Activity this month
- 10.1 days
- Activity this year
- 20.6 days
- Activity to date
- 20.6 days
- Estimate to complete current year
- 32.8 days
- Estimate to complete future years
- 157.5 days