HSS013: LO Grade Reporting

Report Date
April 2016

Achievements this period

An initial meeting with Olwen and Alex to introduce myself and have a quick review of the project objectives.

A meeting with Geir and Myles to introduce myself and review the outline project brief and estimations based on our understandings. 

Project Plan drafted

3 Point Estimate drafted

Requirements Definitions Workshop with key stakeholders to collectively agree specifications

Project Brief issued for sign off

Issues

Revised Planning Milestone from 29/04 to 06/05 approved by WIS

Next Steps

Create BRD/Sign off

Create SDS/Sign off

Develop Student View/Staff View/Desktop Export

Test scripts written

Milestones

Target date

Previous Date

Title

Complete

06/05/16

29/04/16

Planning

NO

12/07/16

30/06/16

Delivery

NO

10/08/16

29/07/16

Closure

NO

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
100.0 days
Activity this month
5.6 days
Activity this year
8.4 days
Activity to date
8.4 days
Estimate to complete current year
53.1 days
Estimate to complete future years
2.8 days

Project Info

Not available.

Documentation

Not available.