TEL034: Lynda.com Implementation

Report Date
April 2016

Achievements this period

An initial meeting with Jenni to introduce myself and have a quick review of the project objectives.

Initial convo's with Dev Tech regarding resource challenges

HR stakeholders identified

Initial convo's regarding Single Sign On

Project Plan drafted

3 Point Estimate drafted

Project Brief issued for sign off but withdrawn and extention to planning Phase from 29/04 to 13/05

Issues

Planning dealys due to unidentified Business Scope

Lynda.com ownership and administration

Next Steps

Business Requirements Document

System Design 

Clarification of integration with LEARN and Moodle

Milestones

Target date

Previous Date

Title

Complete

13/05/16

29/04/16

Planning

NO

18/07/16

18/07/16

Delivery

NO

01/08/16

01/08/16

Closure

NO

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
AMBER
Overall
AMBER
Change Status
Activity
Approved budget
25.0 days
Activity this month
2.4 days
Activity this year
2.4 days
Activity to date
2.4 days
Estimate to complete current year
22.1 days
Estimate to complete future years
0.0 days