Migrations almost complete

Report Date
May 2016

Migrations for all but three servers in L&C have been completed. We remain to finish off some work with the Spacewalk pacth service but that is mostly built and ready. There is one remaining action to produce a list of the RHEL systems that will need to have licences bought in August. We will consolidate the list to maximise the order and any discount that may be achieved across all IS divisions and then recharge to the appropriate cost centres.

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
50.0 days
Activity this month
2.0 days
Activity this year
30.0 days
Activity to date
30.0 days
Estimate to complete current year
4.0 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation

Not available.