Report for April 2016

Report Date
April 2016

Achievements in Last Period

  • Environment setup for dev,beta, test and live CITESTER migrations
  • Started upgrade of CITESTER dev environment to CF11.

Issues

  •  Issue getting Dev Team and Dev Tech resources to complete the CITESTER migrations. See PICCL 2 (https://www.projects.ed.ac.uk/project/inf117/issues/2)
  • CITESTER and Closure Milestones moved as a consequence (however the main project objectives achived as Bamboo upgrade complete)

Next Steps

Project Status
RAG Status
Time
RED
Cost
GREEN
Scope
GREEN
Overall
RED
Change Status
Activity
Approved budget
29.0 days
Activity this month
0.8 days
Activity this year
12.1 days
Activity to date
12.1 days
Estimate to complete current year
9.9 days
Estimate to complete future years
0.0 days