Report for April 2016

Report Date
April 2016

Achievements in Last Period

Environment set-up in DEV still in progress (see issues).

EBIS on-line code deployed in DEV, waiting for environment set-up to be completed.

Issues

Issue with display of Estates Drawings. Uses a piece of third party software autoviz that dosnt work under CF11/ CentOS. As a consequence, project milestones have slipped a further week.

Parallel EBIS On-line development in progress (EST080). Will require careful co-ordination, and possible additional effort by third party integrator.

Next Steps

Complete environment builds (DEV / TEST / LIVE).

Complete DEV sign-off

Complete TEST sign-off.

Deploy to LIVE

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
49.0 days
Activity this month
8.6 days
Activity this year
24.6 days
Activity to date
24.6 days
Estimate to complete current year
27.0 days
Estimate to complete future years
0.0 days