Report for Apr 2016
- Report Date
- January 2016
Achievements in Last Period
Project initiated, 4 kick-off sessions held with Estates stakeholders.
Kick-off technical meeting held.
Issues
Change of Sponsor.
End of planning milestone has moved to 13/05.
Next Steps
Complete project planning phase
Commence analysis phase.
- Approved budget
- 200.0 days
- Activity this month
- 8.1 days
- Activity this year
- 10.5 days
- Activity to date
- 10.5 days
- Estimate to complete current year
- 66.6 days
- Estimate to complete future years
- 125.6 days