Report for April 2016

Report Date
April 2016

Achievements this Period

  • Further monitoring of CF migrations - some completed; all now planned or under way
  • Related wiki pages and reports updated

Issues

  • None reported

Next Steps

  • Continue to monitor planned migrations
  • DRPS migration to be completed
  • Some Windows servers to be migrated by Technology Management team

 

Milestones

30-Jun-2016Windows decommissioning (15-16) completedDeliver
30-Jun-2016RedHat decommissioning (15-16) completedDeliver
30-Jun-2016Solaris decommissioning (15-16) completedDeliver
14-Jul-2016ClosureClose
Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
253.0 days
Activity this month
5.8 days
Activity this year
69.5 days
Activity to date
221.4 days
Estimate to complete current year
32.2 days
Estimate to complete future years
0.0 days

Project Info

Not available.