Status report for April 2016

Report Date
April 2016

Achievement this period

  • Workshops held with Accounts Payable, Accounts Receivable and Financial Accounting

Issues

  • The Project Support Office has left the University so the workshops write-up & future workshop planning is running a bit behind schedule
  • Quick wins identified to-date have not required IS Applications development so very little of the allocated budget has been spent.  The Project Manager and Project Sponsor will need to review whether the budget should be reduced.

Next steps

  • Further workshops planned with SCE, MVM, ISG and Cash Office
  • Bring new Project Support Officer up to speed with workshops
  • Start consolidation and analysis of workshop outputs

 

Target dateTitle
30-Jun-2016Workshops complete
15-Jul-2016Action plans complete
29-Jul-2016Closure
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
100.0 days
Activity this month
3.0 days
Activity this year
16.0 days
Activity to date
16.0 days
Estimate to complete current year
85.0 days
Estimate to complete future years
0.0 days

Project Info