Report for March 2016

Report Date
March 2016

Achievements this period

  • Draft 'as is' process diagrams produced
  • A number of issues and querieshave been flushed out

Issues

  •  Difficulties securing time in business partners' diaries due to volume of other finance work taking place. This has resulted in the delivery date & closure being delayed so the project is being reported on AMBER.

Next steps

  • Clarify outstanding queries
  • Complete 'as is' analysis

 

Target dateTitle
17-Jun-2016End of analysis
30-Jun-2016Closure
Project Status
RAG Status
Overall
AMBER
Change Status
Activity
Approved budget
6.0 days
Activity this month
2.6 days
Activity this year
4.8 days
Activity to date
4.8 days
Estimate to complete current year
1.3 days
Estimate to complete future years
0.0 days

Project Info