February 2016

Report Date
February 2016

Achievements in the last period

  • Planning is now completed for the project and it has passed through governance.

Issues

  • None

Next steps

  • Review project milestones
  • Proceed with analysis and design

 

Milestones

25-Feb-2016Planning
25-Mar-2016Analysis
08-Apr-2016Design
29-Apr-2016Build
24-Jun-2016Acceptance
11-Jul-2016Deployment
22-Jul-2016Deployment Sign Off
29-Jul-2016Project Closure

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
58.0 days
Activity this month
4.0 days
Activity this year
7.0 days
Activity to date
7.0 days
Estimate to complete current year
42.0 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation

Not available.