Report for February 2016
- Report Date
- February 2016
Achievements in Last Period
- Solution for security issue JIRA-25 implemented on DEV and TEST
Issues
- No new issues
Next Steps
- Complete testing and implement on LIVE
- Deployment Review
- Closure
Milestones
| 18-Mar-2016 | Deployment Review | |
| 25-Mar-2016 | Closure |
- Approved budget
- 170.0 days
- Activity this month
- 0.0 days
- Activity this year
- 36.0 days
- Activity to date
- 167.0 days
- Estimate to complete current year
- 3.0 days
- Estimate to complete future years
- 0.0 days