Report for February 2016
- Report Date
- February 2016
Achievements in Last Period
- Project website set up
- Information gathered on tasks for Bamboo upgrades based on experience from previous years.
- Initial discussions with Development Technology, Corporate Services Team and Technology Management to determine which tasks will be in scope for this project.
- Brief written
Issues
- No issues
Next Steps
- Sign off Brief
- Upgrade Bamboo Test
Target date | Title |
---|---|
03-Mar-2016 | End of Planning |
11-Mar-2016 | Build and Acceptance |
21-Mar-2016 | Delivery |
24-Mar-2016 | Deployment Sign Off |
31-Mar-2016 | CITESTER (dev,beta, test and live) Upgraded |
14-Apr-2016 | Closure |
- Approved budget
- 29.0 days
- Activity this month
- 1.0 day
- Activity this year
- 1.0 day
- Activity to date
- 1.0 day
- Estimate to complete current year
- 28.0 days
- Estimate to complete future years
- 0.0 days